Showing posts with label BACK FILLING UPDATE OF HOLY GARDENS OTON. Show all posts
Showing posts with label BACK FILLING UPDATE OF HOLY GARDENS OTON. Show all posts

March 22, 2013

BACK FILLING UPDATE OF HOLY GARDENS OTON, March 19, 2013

Let us have ears that can hear, minds that can understand, hearts that can feel, hands that can do...Let us read and understand these posts.

BACK FILLING UPDATE OF HOLY GARDENS OTON

TOTAL CUBIC DELIVERED 6,667.2 WORTH PHP1,500,000 OUT 
OF PHP1,575,000.00 PESOS . THERE ARE STILL 300 CU TO BE
DELIVERED AS PER RECORD OF THE CONTRACT

Lawn 5 area



Lawn 5 as seen on box culvert



Section of Lawn 5 needing additional filling to become saleable



Saleable Lawn 5 area after soft spreading and is ready for
planting of carabao grass




Portion of Lawn 5 area to be filled up by 300 cu to be saleable