Minutes of the meeting by and between Jorge Saguinsin and Henry Tanedo at BK
at Tiendesitas today February 19 2017
Agenda:
1. GDC
1. Infrastructure: walls building
2. Improvements at the site
3. Agenda from JR:
1. backfilling and levelling of areas near the newly built wall;
2. cleaning the vault area; and moving the container to an area farther away and/or to block
the path of squatters
3. allowing Tatang to put up a shed at the site, to sleep there to guard the site vs the
squatter
4. proposal to have the crematorium at the interior of the park rather than near the entrance
5. building a commercial area near the front of the property due to commercialization of the old provincial road to Midlands/ Tanauan
6. closure of shortages account
4. From AUG
1, Another 60 days promo: 60 months to pay, P48,000 price for selected plots, P800 MA, 0 interest
and selling the other plots using the same scheme
2. Collection of backlog of ME
Deliberation
1. Mr Tanedo congratulates HGGMP and its contractor for a well built wall, however some improvements are in order: (also int he agenda of JR)
1. back filling from current level and maybe compaction (For Morong Lands/GCH MRS
2. moving away the vault manufacturing area from its current location, moving the container van, and cleaning the area. (For Morong Lands GCH MRS
3. cleaning the road: HGGMP staff or red boys of Pete Castillo
For backfilling levelling
For cleaning/clearing near the vault area
Removing the vault area here; perhaps some of the plots here are included in the promo
The triangle area where you must build the embalming room, storage area (at AUG expense)