February 18, 2019

Expense Estimate for additional aircon at our bereavement chapels; proper pricing for chapel use

Question:   Is it justified to charge chapel use for a package?  Say 72,000.00 for a 4 nights 5 days viewing?


                 Broken down as :   P40,000 chapel rental,   32,000 for casket and services...?


Cap Ex:


  For Panga:  4 additional aircon


    Chapel  1  


     2 x 2.5 hp inverter  -   P60k x 2   =    120,000


    Installation charge   say P10,000 x 2    20,000


    Chapel 2


    2 x 2.5 hp inverter      P60K x 2       120,000


    Family room


    1 x 1.5 hp inverter     P40K  x 1        40,000


    Installation charge      x 10k x 3       30,000


Total                                                  330,000.


   9 led flood  lamps for parking:


  2 nakatutok sa labas


  2.  nakatutok sa entrance road


  1 nakatutok sa parking lot


  2.  from chapel and office natutok sa crematorium


  2.  mula sa crematorium nakatutok sa kalsada at parking

      lot  


    Cap ex                                          9 x 3,500            31,500


   Toilet rehab                                       20,000


   labor                                                 5,000


   Landscaping                                     20,000


                                   Total  ;                                     45,000   


                                                                                P406,500



Maintenance


    1 hp = .7457 kW

  1.  Aircon    


       For 2.5 hp. -- 4 x   2.5  x .7457 x  24  hours x P20/kwh       =  3,579.36


       For  1.5    --- 2 x 1.5 x .7457 x  24 hours x   x P20/kwh      =  1,073.80


         Led floodlamps   9 x 30 watts x  12 hours     =                          648.00


        1 maida x 350                                             =                            350.00


       Elec for water service heater    2 x 1.2 x 24 x 20  =                    1,552.00


                                                                                                        7,203.16 



       Depreciation :  1.500,000  +   405,000  =             


              7,620.00/4 nights

                                                                                


            1,905,000/ 5 years/50  cases    


             Total expenses daily                                                             1.905.00


                    

        Total expenses/night for two rooms/day                                    9,108.16



         Expenses per chapel  /day                                                       4,554.10          


         Total expenses x 4 nights and 5 days                                      18,216,32


         If we charge P10k per night                                                    40,000.00


                        GP                                                                         21,783.70


        Thus our pricing is justified if we go by package      


N. B.  Inverter technology can make for 30 to 50% savings


          Potential savings and more profit:                               



          4 x 2.5 HP Aircon Elec consumption per day:                      P3,579. 36


          2 x 1.5 HP   per day                                                             1,073.80


                                                                                                      4,653.16


          less 30%                                                                             1,395.95  x  4 days  =  5,583.79



cc:     Ms. RCG

         Mr. Jeff

         Mr. Don Aboga

        Communication site


--
PAGSASANAY SA TAGUMPAY (Training for Success)



























  Jorge U. Saguinsin

YOUR OFFICES ARE TO REFER TO THESE ON QUESTION ABOUT PRODUCTS information and pricing.  Please RRURAC

Holy Gardens One Stop Shop (Master Brochure)








1.  LET US WORK TOGETHER TO CREATE BEAUTIFUL LIFE STORIES (not worries)

2.  BIDDA:     BELIEVE, INSPIRE, DREAM, DO AND ACT

3.  Read and answer all email and texts.  Be responsible

 4   RRURAC   (Read, Reflect, Understand, Realize Act, Check)  # 3

5.  Makipag TIPAN -  IGALANG ang mga nasusulat:  CCD handbook at MC

     Pag uusapan sa am talk

 YOUR OFFICES ARE OBLIGED ORDERED TO UPDATE  THEIR POSTS AT THE FOLLOWING SITES: (they have been placed here for your easy reference)

   




   Weekly posting  at HolyGardens Communications and Best Pictures










 



Notice:   This email address is a private property of Holy Gardens Group and its contents are private and confidential.    Its contents and attachment  may not be copied nor forwarded to parties other than the ones intended to,  nor can the contents be used other than the original intent  You are advised to delete the message you received if in case it may have been wrongly sent to your good office

No comments:

Post a Comment

1. One of our beliefs is learning. It pays that you learn more to do more Just to survive you have to learn how forage in a forest or raise your food, catch prey

2. In order to discharge your job well, you have to learn your admin plan the process flow and standards.

3. To keep up with changes, you have to learn and read. There is no other way

4. signify that you have read by putting your name on this comment box. Every staff must: post the name on this comment box, or like, agree/will do. Your registering on this comment box is being graded under communication. Observe RRURAC: Read, Reflect, Understand, Realize (apply to reality) Apply, and Check (if it works)
You need to make __comments a month to qualify for promotion under our CCD

Read the posts on this site every AM talk. Many problems arise simply because people do not know what to do, because they did not read this site

We are making sure that you improve yourself, engage yourself in self improvement through this site...






Note: Only a member of this blog may post a comment.