Hiring for Calamba
ReplyDelete1. Using of social networking - posting of hiring and vacancies at Facebook.
2. Printing of tarpaulin of Hiring that will be posted this week not only on HGGMP site but also to crowded places.
3. Hiring leaflets will be included when giving of leaflets.
Billboard lay out
1. Lay out - for follow up today. CD of lay out will be pouched to our SBU not later than Sept. 14, 2011 and will be posted at HGMP site not later than Sept. 19,2011.
Marketing plan
1. hard copy of marketing plan will be printed today Sept. 13, 2011.
Thanks,
Edith ^__^
1. Plan of action for Martinez:
ReplyDeletePermits-secure until wed (Sept. 14,2011)
Reclaiming of boulders and clearing operation-started today (Sept. 13,2011)
Demolition of Mausoleum- will start on Sept 19,2011
Riprap foundation-will start on Sept 26, 2011
Backfilling- will start on Oct 18,2011
Thanks Es Mgb for comments. Let us do it.