November 28, 2011
TO                   :           THE SENIOR MANAGING DIRECTOR
FROM             :           AIREEN S. RICAMARA
SUBJECT         :           SBU VISIT REPORT
| 6 Ps of   SBU visit |  | WHAT DID   I SEE? | WHAT TO   DO NEXT | 
| PURPOSE   OF VISIT | To   monitor and check Holy Gardens Oton Memorial Park operations, documents as   well as receivables including operation, training and marketing. | The   purpose of my visit is to check and correct wrong doings of the staff and   apply necessary disciplinary action.    To put into action all the manageable executions that were   delayed/pending. a.          Trailer b.         Filling Materials c.         Landscaping of Saleable   Area d.         Installation of Steel Gratings | a.   Explanation letter why the repair of Trailer was delayed; b.  Monitor and follow-up schedule of delivery   of filling materials; c.  Train/teach the GT to comply what is being   ordered and instructed ASAP; d.  Talked to fabricator of steel gratings for   the immediate repair of the gratings. | 
| PROCESS | Is   there office decorum, are they in uniform, do they wear ID, do they know   something, do they communicate/speak well, do they know their job, VMBP, MVP. | OFFICE   DECORUM 1.         Michelle   was in her office attire, April Lyn and Gary Torilla were in their uniform. With   their IDs. 2.         The GT   wore green shirts with their IDs too; 3.         New VMBP   were not yet memorized 4.         Interment   Process: the excavated soil were still in the interment site | 1.          Monitor and check daily on their compliance   to proper office decorum; 2.         Request   for new set of uniform for Michelle; 3.         During   AM Talk, let all the staff recite the New VMBP and be able to memorize it by   heart; 4.         Serve a   written memo and require an explanation letter why the standard were not   being followed | 
| PRODUCT | Is   the park presentable; Work   schedule for construction being followed? For maintenance, landscaping? Is   the park clean, presentable and beautiful? Are the grasses tall, are massing,   color contrast, waving, smiling being followed? Do   they have problems with ABCD and Obedience? Do they have sufficient number of   GT? Are there sufficient planting materials and watering irrigation system | The   schedule of construction were being followed except for the steel gratings; The   park was clean and presentable, but when I looked nearer, I saw plastics, old   tarpaulins buried alongside of the fence between crotons; There   were portions with unwanted grass in vault yard. There   is no massing, contrast and waving The   plants planted along side of the fence in temporary interment area were not   consistent “bungi-bungi” ang crotons They   have sufficient planting materials and watering irrigation system. | Steel   gratings must be repaired ASAP by the fabricator;  I   showed with the two GT what I saw and have them removed the garbage; Unwanted   grass in vault yard were removed; Massing   were thought to the two GT in actual so that they understand what is massing; Hire   two Garden Contractor to focus on landscaping and improving the saleable   area. They   have ipa in nursery.  I taught them how   to mix ipa and garden soil with compost.     Purchase   order for carabao grass and Bermuda grass were prepared and purchase of one   (1) wheel barrow for transporting of plants from nursery to the saleable area   being landscaped. | 
| PROBLEMS | Do   they have plenty of problems? Are their problems quickly acted upon or do   they sit on their problems. Are they addressing concerns/problems with   concrete action and solution? | The   problem with HGOMP staff is communication and proper time management. Hiring   is also the big problem because they were under staff. Interviewed   and gave exam to one applicant for CSS | I   made it clear that all communications must be properly addressed to me so   that if there were problems, it will be properly addressed and acted upon. Documents   of applicant were submitted to head office and exam for evaluation and   checking. | 
| PLANS | Do   they plan their work, and work on their plan.    Do they prepare ahead of time? Do they follow their plans? Do they   monitor progress of plan and inform peers and top management of the   progress/landmarks of their plans? | The   GT does not have their notebook/planner. They have plan with their work   schedule, but it was not written on their notebooks/planner. The   office staff including TS have their planner and written their plan for the   day, prospects, accomplishments for the day | I   demanded the two GT to have a notebook/planner for easy monitoring and   checking of their accomplishment, so that they have written records of what   they have achieved for the day. The   office staff will continue and improve their planning by sending to me their   daily plan and accomplishment via skype of email. | 
| PROFESSIONALISM | Do   they act professionally? Are they engaged in personality development? Are   they more mature? Do they know more? Do they have the right attitude? | They   are not engaged in personality development but they are presentable   enough.  They lack maturity and needs   more improvement in terms of Personal Mastery. | Make   sure that TOES is being done weekly.    Assigned topic for their book reports.  Regular   monthly visit is needed to monitor and check | 
MANAGEABLE EXECUTIONS
WHAT TO DO NEXT:
| WHAT | WHEN | WHO | WHO WILL   CHECK/MONITOR | 
| Trailer Repair | December 1 *Ginamit   pansamantala until Nov. 3 fo excavation | Samson & Joemel | ASR / GCH | 
| Delivery   of     Filling Materials        | November 28 Delivered within 10 – 14 days | Jaime   & Jay / Michelle | ASR / GCH | 
| Landscaping   of Saleable Area | November 28 December 1 | Samson & Joemel Garden Contractor | ASR / GCH | 
| Repair   of Steel Gratings & Installation | November 29 | Robert Japitana | MEF / ASR | 
| Installation   of Hook for Trailer in Eagle | December 4 | Gary & Samson | ASR | 
ACMO
 
 
Thank you Aireen. You did better professionally this time.
ReplyDeleteJUS
Hi Aireen please follow too the SMART requirements especially the T - timeline to do the things you specified. We must do these things sooner/soonest. Please. They were pending before; there is no point that we are not clear as to when they will be done with the follow up. We must set clear goal and objectives as we solve the problems, remove difficulties
ReplyDelete