September 10, 2011

Preparation of SBU's for November 1


DATE              :           SEPTEMBER 08, 2011
TO                   :           JORGE U. SAGUINSIN
FROM             :           ENGR. GILBERT C. HAYLO
RE                   :           PREPARATION OF SBU’S FOR NOVEMBER 1

  1. HGLUMP                                                                                SCHEDULE
1. INSTALLATION OF LIGHTS FOR NOV 1                            OCT.10-15, 2011
      -as shown on the lay out HGLUMP needs to provide
      10 pcs of metal halide lamp.
      - HGLUMP had already  assorted & reserve electrical
      Wires for installation
2. FABRICATION & INSTALLATION OF WATER TANK (1,000 LITERS)
      -Cost of the project Php 99, 000.00
3. CONSTRUCTION OF PUBLIC TOILET- 60sqm-    UNDECIDED because  
                                                                                          According to Edith & HLC
                                                                                          They can’t provide the
                                                                                          Budget

  1. HGPMP
1. INSTALLATION OF LIGHT FOR NOV 1-                            OCT 3-8, 2011
      -as shown on the layout HGPMP needs to provide
      9pcs of metal halide lamp.
      -HGPMP had already reserve electrical wires for
      Installation.
2. FABRICATION & INSTALLATION OF WATER TANK (1,000 liters) Sept 19-
                                                                                                                       Oct 1, 2011
      -Cost of the project Php 99, 000.00
      -It will be constructed with stand
3. HGPMP-had already public toilet through chapel

  1. HGGMP
  1. RE-CONDITIONING OF EXISTING METAL HALIDE LAMP
& ADDITIONAL METAL HALLIDE FOR LAWN 6 & MAUSOLEUM AREA
      -as shown on the layout HGGMP needs to provide 9 pcs of metal halide lamp.
      -HGGMP needs to provide extra wires for the installation of additional lamp.
2. FABRICATION  & INSTALLATION OF WATER TANK (1,000 liters)  Sept 19-
                                                                                                                       Oct 1, 2011
      -it should be installed on the roof of the chapel/CR
      -cost- Php 40, 000.00
3. HGGMP had already public toilet @chapel

  1. HGCMP
1. INSTALLATION OF LIGHTS FOR NOV 1                                        Oct 3-8, 2011
      -As shown on the layout HGCMP needs to provide 4 pcs of metal halide lamp
      -they will also provide wires for installations.

  1. FABRICATION & INSTALLATION OF WATER TANK (1000 liters) – Sept 19
Oct 1, 2011
      -cost of the project Php 99, 000.00
      - it will be constructed with stand

3. CONSTRUCTION OF PUBLIC TOILET-60 sqm       - UNDECIDED
      -cost of the project- Php 700, 000.00
      -the location is not yet ready

  1. HGOMP
1.INSTALLATION OF LIGHTS FOR NOV 1                 Oct 10-15, 2011
      -layout to follow

  1. HGOMP had already portable water tank
  2. Construction of public toilet-60sqm                               UNDECIDED
-Cost of the project Php 700, 000.00



Prepared by:

Engr. Gilbert C. Haylo

 


1 comment:

  1. Please submit a plan that can be funded and that can be done. The output of that is a minutes document called PDCA.

    Let us work us a team even with the proposals.

    JUS

    ReplyDelete

1. One of our beliefs is learning. It pays that you learn more to do more Just to survive you have to learn how forage in a forest or raise your food, catch prey

2. In order to discharge your job well, you have to learn your admin plan the process flow and standards.

3. To keep up with changes, you have to learn and read. There is no other way

4. signify that you have read by putting your name on this comment box. Every staff must: post the name on this comment box, or like, agree/will do. Your registering on this comment box is being graded under communication. Observe RRURAC: Read, Reflect, Understand, Realize (apply to reality) Apply, and Check (if it works)
You need to make __comments a month to qualify for promotion under our CCD

Read the posts on this site every AM talk. Many problems arise simply because people do not know what to do, because they did not read this site

We are making sure that you improve yourself, engage yourself in self improvement through this site...






Note: Only a member of this blog may post a comment.